At 6718 Lowell Avenue, the sales site for The Lowell says "Only a Few Homes Remain" and invites buyers to tour the model homes. Winthrop Development built 44 condominium residences there. In 2019 the Tysons Reporter covered the project as a proposal identified by its site address, 6707 Old Dominion Drive. So the most recent new condo building in downtown McLean took years to go from proposal to models, and its remaining supply is now down to a handful of units.

Since then, Fairfax County has approved more downtown housing, and more proposals are in line behind it. Very little of that housing is guaranteed to be condos a buyer can own. The one approved condo building now has a pending application to replace it with something else.

The one approved condo building may never be built

In May 2024, the Fairfax County Board of Supervisors approved a five-story, 104-unit condominium building at the McLean Professional Park, 1477 Chain Bridge Road. The developer was T&M McLean Ventures, and the plan included a 192-space underground garage. Of the downtown projects approved since the county adopted its 2021 plan for the McLean Community Business Center, it was the only one set up as for-sale condos from the start.

FFXnow reported in September that Sunrise Senior Living has a contract to buy part of that site. On Sept. 2, 2026, Sunrise filed a rezoning application for a continuing care facility with 145 independent living units on the land. It would expand the company's adjacent Sunrise at McLean Village community at 1515 Chain Bridge Road. The proposed building would match the condo plan's size and height and have roughly the same square footage.

As FFXnow reported it, Sunrise's application says the approved condo, with its large units at high price points, would likely attract the same demographic as the independent living building. The difference is that the Sunrise building would add on-site services. FFXnow also reported that, under the purchase contract, the condo approval stays available if the sale does not go through. The site now has two possible futures, and only one of them includes condos for sale.

For a buyer, this matters because the developer of a for-sale building is competing for the same land with an operator who would hold and run the building. Downtown McLean parcels are small and hard to assemble. When another use can pay for a site, the condo version becomes the fallback.

The pipeline, sorted by who can own the units

Below is each downtown project in the research, sorted by tenure. Tenure answers the question a buyer cares about, which is whether a unit could ever be bought.

Project Address Homes Tenure Stage as of November 2026
The Lowell, Winthrop Development 6718 Lowell Avenue 44 Condominium Built; marketing its remaining homes
McLean Professional Park, T&M McLean Ventures 1477 Chain Bridge Road 104 Condominium Approved May 2024; Sunrise rezoning filed Sept. 2, 2026
Sunrise Senior Living expansion 1477 Chain Bridge Road 145 Continuing care, independent living Rezoning application filed Sept. 2, 2026
Astoria at McLean, JAG Partners 6854, 6856, 6858 Old Dominion Drive and 6861 Elm Street Up to 130 Not announced Approved Oct. 24, 2023; site plan in county review
McLean Office Center, Cypress Real Estate Company 1368 Beverly Road 56 Rental apartments Approved March 17, 2026
Highcrest 6816 and 6824 Elm Street 115 Not decided Rezoning in review; Planning Commission hearing scheduled for March 2027

Add up the approved rows: Astoria, the Professional Park condos and the Cypress building come to 290 homes. Only 104 of them were approved as condos, and those are the ones a pending application would replace. Cypress's 56 are rentals. Astoria's 130 have no announced tenure. In 2023, FFXnow reported that JAG Partners had not said whether the building would hold rentals or condos, and the county's rezoning record approves "multifamily dwelling units" without specifying either.

Highcrest is keeping its options open too. Highcrest President Colin Dean told FFXnow that the company had not decided between rental apartments and for-sale condos. The seven-story building would offer studios through three-bedrooms, some with dens, plus a 223-space underground garage. Its 6816 Elm Street site currently holds a Keller Williams Realty office, the brokerage brand our team works under. The plan includes about 16,371 square feet of office space, and Keller Williams would return to it after construction.

A Board vote is the first county approval, and more follow

A buyer reading "approved" in a headline may assume construction is close. Astoria shows how long the steps after the vote can take. Here are its county records in order:

  1. Rezoning. The Board of Supervisors hearing date is listed as Oct. 24, 2023, for up to 130 multifamily units.
  2. Site plan. The county's site plan record shows the case "In Review," with fee entries dated Oct. 27, 2026, and no completed inspections.
  3. Record plat. The related plat record is marked "Waiting for Corrections."

Three years after the vote, the project is still working through engineering review, and its tenure is still undecided. The Lowell went from a 2019 proposal to a building now selling its last homes. On that track record, a downtown condo approved today would be a long-range option for a buyer, not something to plan around this year.

Some of the delay comes from the land. When Cypress's Beverly Road project was approved, FFXnow reported that the developer had struggled to persuade neighboring owners to combine their parcels into a larger site. The approved building sits on 0.56 acres. An affiliate of Highcrest bought the three-story office building at 6824 Elm Street on Feb. 19 for $4.5 million, a price that county records said reflected "anticipated redevelopment." When small parcels change hands at prices that already assume redevelopment, the developer has to pick the product that earns that price back, and rentals or senior housing can make that math work.

Why the regional condo surplus doesn't reach downtown McLean

Across Northern Virginia, condo buyers have more choice than they did a year ago. The Northern Virginia Association of Realtors' September 2026 report found that active listings rose 30.7% from September 2025, to 3,477. Condo and townhome inventory rose 49.7%, while detached-home inventory rose just 5.7%. Months of supply reached 2.5 in September 2026, and average days on market held at 28. The median sold price rose 4.2% to $744,950.

Those figures cover Fairfax and Arlington counties, Alexandria, Falls Church, and several towns. The added condo inventory comes from communities that already have many condos. McLean has very few. Approximately 93% of McLean's existing housing units are single-family detached homes, according to FFXnow's reporting on Fairfax County data. A 49.7% jump on a large base of condos creates real choice. The same jump on McLean's small base adds only a few listings.

That leaves a buyer who wants a condo specifically inside McLean's downtown with a short list. It includes resale units in older buildings, the remaining homes at The Lowell, and a pipeline where the only approved condo building faces a competing application.

Using this when you price and negotiate

The pipeline affects how a buyer should read a downtown McLean condo listing:

  • New supply is not about to undercut today's prices. The approved condo count may go to zero if Sunrise's sale closes, and the projects with undecided tenure are still under county review. A seller of a downtown resale condo is not competing with a delivery date.
  • Your leverage will come from comparable sales, not from future competition. In a segment with this few units, a handful of recent comparable sales sets the pricing argument. Building that argument carefully counts for more than citing regional inventory headlines, because those headlines describe other markets.
  • Projects with undecided tenure are worth watching as possible future condos. Astoria and Highcrest could each add for-sale homes, and each is still years from residents moving in. Highcrest's Planning Commission hearing is scheduled for March 2027.
  • Downtown rentals and senior housing add homes but not ownership. Cypress's 56 apartments include at least seven workforce dwelling units and 2,120 square feet of ground-floor retail. Those homes add to downtown activity. They do not add units a buyer can purchase.

Questions buyers ask about downtown McLean condos

Is the 104-unit condo approval at 1477 Chain Bridge Road still valid? According to FFXnow's September reporting, yes. Sunrise's purchase contract keeps the condo approval as an option if the sale does not close, and Sunrise's own plan requires a separate rezoning. The county's rezoning record for the Sunrise application is where updates will post.

Will Astoria at McLean have condos? JAG Partners has not announced a tenure, and the county approval allows up to 130 multifamily units without specifying rental or condo.

Where can I follow these projects myself? Each project has a public case in Fairfax County's PLUS system, and the county's McLean Community Business Center planning page explains the 2021 plan behind them.

If you're considering a condo in downtown McLean, it helps to know which of these buildings could actually be offered for sale and when, before you decide what to pay for a resale unit today. Paula Heard and The Heard YOU Team track these county cases and use that record when building the comparable-sales case for your offer. Schedule a Free Consultation to price a specific McLean condo against the current pipeline.